Our Clients
Project Profiles
Projects

Nuclear Turbine Building Roof Replacement Project
PPL Electric Utilities Corporation
Susquehanna Steam Electric Station
Berwick, Pennsylvania

PROJECT DESCRIPTION:

InMarch of 2000, PPL Electric Utilities Corporation contracted with Potteiger-Raintree, Inc. to complete a time critical roof replacement project of the nuclear Turbine Building at the Susquehanna Steam Electric Station in Berwick, Pennsylvania.

This project was to be a two (2) year phased project that defined "fast-track" construction. It required an immediate start, extremely short duration
and a time critical completion date.


Project Details:
  • Building is 130' in height. Access for employees was via a freestanding 140' tall stair tower. All debris removal and all new materials were hoisted to the roof by a 110 ton crane.
  • Existing 20+ year old coal tar pitch built-up roof system was removed.
  • New 20 year warrantied coal tar pitch built-up roof system was installed.

Project Challenges:

  • We were required to mobilize 25-30 men for nuclear, safety and security/site access training within one week after receiving contracts:
  • In order to keep our existing roofing projects manned, fellow TectaAmerica member GRS/Greenberg Roofing was able to provide additional manpower needed for this project.
  • Included a complete FBI 5 year criminal background investigation on each employee.
  • Included a 10 panel pre-job drug test for all employees.
  • Included physiological testing for pre-qualification.
  • Work could only be completed during Outage. There would be no option for completion time extension.
  • Over 50% of available work days were lost due to snow, rain and high winds.
  • Odor issues necessitated moving the asphalt and coal tar pitch kettles 200 yards away from crane hoisting area.
  • Security precautions required that each item of new roofing material was x-rayed or individually hand inspected by security guards.

Epilogue:

Each phase of this fast track project was completed on time and within budget with over 108,000 SQ FT of re-roofing completed within a total of 32 working days. This work was finished despite the unique conditions of problematic site access conditions, prohibitive security measures, stringent nuclear safety criteria, extensive training requirements and inclement weather.

Deer Point Condominiums Project
North Dorchester High School
The Cathedral Baltimore, MD
Virginia State Supreme Court Alexandria, VA
PPL
Allfirst Bank